The AMCA first flight 2028 target and the tender meant to deliver it point to different years. Defence Secretary Rajesh Kumar Singh has said the first Advanced Medium Combat Aircraft (AMCA) prototype should fly in September 2028. The Request for Proposal (RFP) gives the winning partner up to 30 months from contract signing. Bids close on 30 October 2026 and open the next day, so a contract signed in early 2027 puts the RFP’s outer limit near September 2029.
Why the AMCA first flight 2028 Target and the RFP Clock Do Not Line Up
The two figures come from different documents. The Defence Secretary gave the September 2028 date as a programme objective at the NDTV Defence Summit on 27 September 2026. The RFP’s 30 months is a contractual limit, and the same schedule reportedly requires all five prototypes within 64 months and a 1,800-sortie flight-test programme within 84 months.
For a September 2028 flight to fall inside a 30-month window, the clock would have had to start in March 2026, two months before the RFP was issued on 27 May. Selection is reported to follow bid submission by four to five months, which points to February or March 2027, according to reports on the RFP. A contract then would carry the 30-month limit to about September 2029.
The 64-month limit for five prototypes lands in mid-2032, which matches the 2032 horizon in earlier reporting on the programme.
This is TES’s reading, not an official statement. The 30 months is a ceiling, and a partner can fly sooner. ADA, the Aeronautical Development Agency, keeps design authority, so the aircraft is not being drawn from a blank sheet. Even so, the AMCA first flight 2028 objective leaves little margin for the steps that come first.
Three Groups Are Bidding, and 31 October Opens Evaluation, Not the Contract That Starts the AMCA Clock
Three groups are in the contest. The submission deadline of 30 October 2026, 3 pm, with opening on 31 October, has slipped twice already: bids were first expected in late July, then late August, before ADA’s Corrigendum-3 of 27 August set the October dates.
Opening starts technical evaluation, and the commercial stage follows. The RFP also requires the winner to form a new company within three months of selection, with Indian residents holding the majority, so the contract is the start of a corporate build and not only a manufacturing order.
| Bidder | Members | What it brings |
|---|---|---|
| Tata Advanced Systems | Bids alone | Set up the C-295 final assembly line at Vadodara with Airbus, inaugurated in October 2024 |
| L&T-led group | Larsen & Toubro, Bharat Electronics Limited (BEL), Dynamatic Technologies | Heavy manufacturing paired with defence electronics |
| Bharat Forge-led group | Bharat Forge, BEML, Data Patterns | Precision engineering, large-scale military production, and radar and avionics electronics |
TES summary of the shortlisted bidders.
In TES’s assessment, fighter-class final assembly would be new for all three. The selected partner builds five flying prototypes and one structural test aircraft, and the prototype phase is government-funded at roughly ₹15,000 crore.
Engine, Tooling and Puttaparthi Are Where the AMCA first flight 2028 Date Can Slip
The prototypes are reported to use the GE F414, so engine delivery sets one clock. TES has covered why jet engines remain India’s longest gap. The 120 kN engine reportedly planned with Safran is for a later variant, so it does not bear on the prototype clock.
The second variable is infrastructure. Defence Minister Rajnath Singh laid the foundation stone for ADA’s Aircraft Integration and Flight Testing Centre at Puttaparthi, Andhra Pradesh, on 15 May 2026, as the Press Information Bureau announced. The runway there is reported to be extended to 10,000 feet. TES has looked at what the Puttaparthi hub is meant to do.
Both variables depend on a partner that does not yet exist as a company. A funded private partner with a first-flight deadline written into the contract is a different footing from earlier design-agency schedules, and it gives the AMCA first flight 2028 target a defined test.
HAL Is Outside the Prototype Contest, Not Outside the Programme
Hindustan Aeronautics Limited (HAL) is not among the three shortlisted groups, and the Defence Secretary has attributed this to routine technical grounds. TES covered the private sector versus HAL question when it first surfaced.
The Indian Air Force is expected to float a separate large procurement tender once prototypes complete testing, and HAL is expected to take part. The aim is a second national fighter line alongside HAL’s Tejas line. The Tejas programme shows why: it first flew on 4 January 2001, 18 years after sanction in 1983, and Mk1A deliveries are still the market’s open question.
What to Watch After 31 October
Will the bids open on 31 October as scheduled?
ADA’s schedule says yes, but the deadline has moved twice since the RFP was issued. A fourth corrigendum would be the first sign of another slip, and each month of delay moves every 30-month limit by the same month.
When will the partner be selected?
On the reported four-to-five-month schedule after submission, selection falls in February or March 2027. The contract signing date matters more than the selection date, because every limit in the RFP counts from signing.
Can the AMCA first flight 2028 date still hold?
Nothing in the RFP forbids it. A first flight in 2029 would sit inside the RFP, while the AMCA first flight 2028 goal would require the partner to beat its own deadline by about a year.
What must the new company show first?
It must be formed within three months of selection with an Indian-resident majority. Its first manufacturing commitments at Puttaparthi will show how fast the programme can move. TES tracks the programme on its India military platforms hub.
The Indian Air Force, which has no radar-evading stealth fighter in service, gains more from a date fixed on a signed contract than from an ambitious one that moves. That makes the signing date the number to follow after 31 October.