Nearly seven years have passed since the Ministry of Defence announced that development trials of a mobile Army air-defence missile were complete, on 23 December 2019. The Anant Shastra missile system, formerly the Quick Reaction Surface-to-Air Missile (QRSAM), is built to travel with armoured columns. In September 2025 the Army issued a request for proposals to Bharat Electronics Limited (BEL) for five to six regiments, reported at about ₹30,000 crore ($3.2 billion). As of 15 November 2026, TES has found no Ministry of Defence announcement of a signed production contract.
Three developments give the wait fresh weight. The Defence Acquisition Council (DAC) cleared Medium Range Surface-to-Air Missile (MRSAM) and Very Short Range Air Defence System (V-SHORADS) purchases for the Army on 3 July 2026. The fifth S-400 squadron is due this month, by several reports. And the Indian Air Force’s Maintenance Command used a seminar on 15 November to argue that an air-defence system is only as good as its availability on any given day.
What the Anant Shastra missile system does for moving armour
According to DRDO and the Ministry of Defence, the system can search and track targets while moving and fire after a short halt. Two four-faced active-array radars give 360-degree coverage, and the stated missile range is about 30 km. A DRDO official told The Hindu in December 2020 that it was the first indigenous on-the-move air-defence system, meant for the Army’s Strike Corps, with an engagement ceiling of about 10 km.
A weapon system has four elements: a fully automated command-and-control system, a battery surveillance radar, a battery multifunction radar and a launcher. The missile is a single-stage solid-propellant design with inertial mid-course guidance, a two-way datalink and an active seeker for the terminal phase. The same 2020 official said the launcher carries six missiles that can engage six targets, and put indigenous content at 90 per cent, rising to 99 per cent in stages.
These figures predate the 2022 flight tests, and TES has not found a current official specification sheet.
Reports citing Ministry officials say it will replace the ageing Soviet-origin Osa-AK and Kvadrat systems, and it is to be integrated with Akashteer, the Army’s automated air-defence command network.
Mobile cover for moving armour has a long record. In October 1973, Egyptian and Syrian formations used mobile SA-6 missiles and radar-guided ZSU-23-4 guns to protect their armour, and the Israeli Air Force lost about 50 aircraft in the first three days of the war, by one military-history account. Armour that moves needs defences that move with it.
Anant Shastra missile system milestones from development trials to the contract stage.
Why seven years passed between trials and the contract stage
The Ministry of Defence announced completion of development trials on 23 December 2019. DRDO and the Army completed six flight tests in September 2022, according to the Press Information Bureau (PIB). The MoD Annual Report 2025-26 records that technical and user trials are complete and that the DAC granted Acceptance of Necessity, the first approval stage, in July 2025 for induction into the Army and the Air Force.
Expected dates have moved more than once. In December 2020 a DRDO official said the system would be ready for production the following year. In January 2023 a DRDO senior technical officer told The Hitavada that production could start within six months of a green signal from the Ministry.
After the Army’s request for proposals to BEL in late September 2025, one report expected deliveries from early 2026 and another said the contract could be finalised by the end of 2025. Around the end of June 2026, BEL management told analysts that government approval was expected in the coming weeks, according to market reports.
| Date | Milestone | Source type |
|---|---|---|
| 23 December 2019 | Development trials declared complete | MoD statement |
| December 2020 | DRDO official: production-ready “next year” | The Hindu |
| September 2022 | Six flight tests with the Army | PIB |
| January 2023 | DRDO: production within six months of a Ministry green signal | The Hitavada |
| July 2025 | DAC Acceptance of Necessity for Army and Air Force induction | MoD Annual Report 2025-26 |
| Late September 2025 | RFP to BEL for five to six regiments, about ₹30,000 crore | Press reports citing officials |
| About end June 2026 | BEL management: government approval expected in coming weeks | Market reports |
| 15 November 2026 | No signed contract announcement found by TES | TES review |
TES has not found an official explanation for the interval. Procedure accounts for part of it: approval, tender, price negotiation, then government sanction and contract. An RFP is the second stage of that sequence, The Tribune reported. The ₹30,000 crore figure is the reported estimated value of the tender and not a signed contract value. The Ministry has responded with a July 2025 approval, a September 2025 RFP and a named lead integrator, and the next step is the one BEL management described.
How the Anant Shastra missile system differs from Akash, MRSAM, V-SHORADS and the S-400
The difference is not range. The stated 30 km matches the 30–35 km reported for Akash Prime, which the Army will also field in new regiments. The difference is the sensor and the tempo: search and track on the move, firing after a short halt. A DRDO official called it the first indigenous on-the-move air-defence system. A brokerage note describes it as complementing MRSAM and Akash.
| System | Role | Stage (official or reported) |
|---|---|---|
| V-SHORADS | Very short range, man-portable class | DAC AoN, 3 July 2026 (PIB) |
| Anant Shastra (QRSAM) | Mobile; search and track on the move; about 30 km | AoN July 2025; RFP September 2025 |
| Akash Prime | Area defence for mobile and static assets; 30–35 km reported | Two high-altitude targets destroyed in Ladakh (MoD Annual Report 2025-26); third and fourth Army regiments, per reports |
| MRSAM (Army) | Medium range, 360 degrees | Four flight tests April 2025; DAC AoN 3 July 2026 |
| S-400 | Long range | Fourth squadron delivered mid-2026; fifth due November 2026, per reports |
TES has examined the top tier in its analysis of the S-400’s 314 km kill during Operation Sindoor and the wider architecture in its report on Mission Sudarshan Chakra and Project Kusha. The same DAC meeting of July 2026 also cleared man-portable anti-tank missiles, covered in TES’s piece on the Javelin deal and MPATGM.
Reports citing officials say existing Akash and MRSAM systems, with the Air Force, countered Pakistani drones in Operation Sindoor. Anant Shastra is not reported to have been in service then, and the Ministry has not published an assessment of how any system performed, so TES draws no performance conclusion from the operation. The Tribune reported that the Army moved to acquire it months afterwards.
Who builds the Anant Shastra missile system, and what the order means for BEL and BDL
BEL is lead integrator, according to reports on the tender. A December 2020 report said BEL makes the radars and control systems, Larsen & Toubro (L&T) the launcher and Bharat Dynamics Limited (BDL) the missiles. A brokerage note expects the missile award to flow to BDL, and another cited sources who put BDL’s share between ₹10,500 crore and ₹12,000 crore, roughly a third to two-fifths of the full value. That is an estimate, not a disclosed contract term.
Market reports sometimes treated the tender as an order. BEL closed FY26 with an order book of ₹73,882 crore, and its guidance excluded this contract, according to a market report citing BEL management; a signed order would take the book past ₹1 lakh crore for the first time. BEL and BDL shares rose more than 2 per cent on the day the tender was reported in September 2025. A signed contract with a delivery timetable would be new information.
The order sits inside a wider shift TES has tracked: the Ministry opening tactical missile production to private firms, covered in TES’s report on India’s private missile manufacturing. TES also reported BEL’s ₹770 crore LLLR-I radar contract for the Army.
Takeaway. The Anant Shastra missile system has a design whose trials the Ministry reports as complete. The open question is delivery: how many regiments, by when, and with what support.
Whether the Army can keep the Anant Shastra missile system ready once fielded
Readiness will decide the value of the order. On 15 November 2026, the Indian Air Force’s 13 Base Repair Depot marked fifty years with a seminar on “Air Defence 2040: Sensors, Networks and Sovereign Sustainment” in New Delhi, according to PIB. Air Marshal Yalla Umesh, Air Officer Commanding-in-Chief of Maintenance Command, said an air-defence system’s effectiveness lies in its operational availability, and that sustainment must be built into equipment design and induction.
He defined sovereign sustainment as the ability to diagnose, repair and restore sophisticated systems within the country. On the same day, Raksha Mantri Rajnath Singh told a national conference on non-destructive testing that quality is an essential element of operational reliability in missiles, aircraft, naval platforms and spacecraft, and that there can be no compromise on the integrity of testing results in strategic applications.
Neither release refers to Anant Shastra, and the depot serves the Air Force. The link is TES’s assessment. The system depends on two active-array radars, so radar uptime, spares and indigenous test equipment will shape how many of the planned regiments are ready on any given day. The Annual Report lists Air Force induction as well as the Army’s; no source TES found says which maintenance chain would support it.
What to watch next on the Anant Shastra missile system
- When will the contract be signed?
- No date has been announced. BEL management indicated around June 2026 that government approval was the next step. BEL, as a listed company, would be expected to disclose a contract on the stock exchanges (TES assessment).
- Who will operate it?
- The Army issued the tender for five to six regiments. The MoD Annual Report 2025-26 lists induction into both the Army and the Air Force.
- What would a signed contract settle?
- The delivery schedule, the number of regiments and the support terms. Those three details would turn a design reported as trial-complete into fielded capability.
The first delivery date will be the number to hold the programme to. India has a mobile air-defence design that completed development trials in 2019, flew six tests with the Army in 2022 and won approval in July 2025. The next step is industrial and administrative: whether approval, contract and production follow in time to put batteries with the Army.